loading

Building the scheme

Building the scheme

Updates on phasing plan/works programme, and other key updates will be available here.


Weekly email

Open weekly email in new window


Progress Update

The major construction works associated with the scheme have now been completed. You will notice a reduced presence of our contractor FM Conway on-site. Surface treatment works are underway and are the only remaining activity left as part of Phase 4.

Summer Works

Our maintenance team are on-site dealing with defects and snagging issues that have been reported to us.

If you would like to raise a defect for the maintenance team to address please do so via: https://www.westminster.gov.uk/report-it

Alternatively, to report a problem with a traffic signal please using the following link: https://tfl.gov.uk/help-and-contact/contact-us-about-streets-and-other-road-issues

Several lighting columns still require connecting to the electricity network. Consequently, UK Power Networks will be on-site working to address this in collaboration with our team. The works will involve some small-scale excavation of the footway to gain suitable access. Footways will be properly reinstated.

Autumn 2019 - December 2019

During October, traffic surveys will be undertaken as part of the Monitoring Strategy. The results will be analysed and compared with traffic data that was collated before the implementation of the scheme. The purpose of this exercise is to ascertain how the switch to two-way operation has affected traffic patterns. A report will be published in December detailing the outcomes and any mitigation that may be required.

Surface Treatment Works

This involves the application of high friction anti-skid material on the approaches to signal controlled junctions and buff-coloured material at pedestrian crossings and the raised tables.

High friction surfacing is a highly effective surface treatment proven to increase the skid resistance of asphalt roads. This material is installed over new asphalt in advance of most signalised junctions. The buff coloured material at pedestrian crossings points and raised tables is designed to provide a visual warning to drivers and act as a traffic calming feature.

Please note that these works will be delivered through night-time road closures. Work is taking place during the night to minimise the impact to traffic. Whilst there will be some noise, this will be significantly quieter compared to carriageway resurfacing. Our teams have been reminded to keep noise to a minimum and be respectful of local residents trying to sleep. We do apologise for any disturbance caused.


Revised Surface Treatment Schedule

The revised dates for the surface treatment works have been issued and are detailed below. A total of 13 night-time road closures are scheduled to take place over the next 3 weeks.

Please note that these dates remain provisional, subject to prevailing weather and traffic conditions.

Road closures will only apply to the carriageway. Footways will remain open to pedestrians. For information on the impact to bus services please refer to leaflets in the bus shelters or visit https://tfl.gov.uk/bus/status/.


Week Commencing Monday 22nd July

Monday 22nd July 2019 00:00 - 05:00

  • Gloucester Place, Park Road and Baker Street, will be closed to all traffic between Rossmore Road and Marylebone Road.
  • All traffic will be diverted via St John's Wood Road and Edgware Road.

Monday 22nd July 21:00 until Tuesday 23rd July 06:00

  • Melcombe Street (between Gloucester Place and Glentworth Street) and Melcombe Place / Dorset Square (between Marylebone Station and Gloucester Place) will be closed to all traffic.

Tuesday 23rd July 21:00 until Wednesday 24th July 06:00

  • Baker Street will be closed southbound only between Blandford Street and Fitzhardinge Street.

Wednesday 24th July 21:00 until Thursday 25th July 06:00

  • Portman Square will be closed southbound only between Fitzhardinge Street and Wigmore Street.

Thursday 25th July 21:00 until Friday 26th July 06:00

  • Orchard Street will be closed southbound only between Wigmore Street and Oxford Street.

Friday 26th July 21:00 until Saturday 27th July 06:00

  • Orchard Street will be closed northbound only between Wigmore Street and Oxford Street.


Week Commencing Monday 29th July

Monday 29th July 21:00 until Tuesday 30th July 06:00

  • Portman Square will be closed northbound only between Wigmore Street and Fitzhardinge Street.

Tuesday 30th July 21:00 until Wednesday 31st July 06:00

  • Baker Street will be closed northbound only between Fitzhardinge Street and Blandford Street.

Wednesday 31st July 21:00 until Thursday 1st August 06:00

  • Gloucester Place will be closed southbound only between Blandford Street and Upper Berkeley Street.

Thursday 1st August 21:00 until Friday 2nd August 06:00

  • Portman Square and Portman Street will be closed southbound only between Upper Berkeley Street and Portman Mews South.

Friday 2nd August 21:00 until Saturday 3rd August 06:00

  • Portman Street will be closed southbound only between Portman Mews South and Oxford Street.


Week Commencing Monday 5th August

Monday 5th August 21:00 until Tuesday 6th August 06:00

  • Portman Street will be closed northbound only between Oxford Street and Seymour Street.

Tuesday 6th August 21:00 until Wednesday 7th August 06:00

  • Portman Square and Gloucester Place will be closed northbound only between Seymour Street and George Street.

Wednesday 7th August 21:00 until Thursday 8th August 06:00

  • Rossmore Road will be closed to all traffic between Harewood Avenue and Park Road.



Construction Drawings

70004404-03-BS-01-KEY.pdf

70004404-03-OA-GA-01.pdf

70004404-03-OA-GA-02.pdf

70004404-03-OA-GA-03.pdf


About the project

About the project

Improved streets for the local community.

Welcome to the Baker Street Two Way Project website. The project aims to transform Baker Street and Gloucester Place into pleasant streets where people can get about easily and safely, relax and spend time.

The aim of the project is to reduce the dominance of traffic along Baker Street and Gloucester Place which divides up the area, creating access and safety problems.

The evidence shows that one way traffic down Baker Street and up Gloucester Place, which often resemble urban motorways, is at the heart of these problems. The wide carriageways encourage high traffic speeds, particularly during quieter periods of the day. When traffic volumes are highest during the peak periods, there is congestion southbound on Baker Street approaching Marylebone Road and Oxford Street and northbound on Gloucester Place approaching Marylebone Road.

By reintroducing two way traffic flow along Baker Street and Gloucester Place and complementary improvements to the public realm in the area, the project will make the whole area more pedestrian friendly and accessible and restore the unique Marylebone character.

The Baker Street Two Way project is being delivered by Westminster City Council and Transport for London. The project is also supported by the Baker Street Quarter Partnership and The Portman Estate.

This is an opportunity to rebalance road space and traffic signal time to provide greater benefit to pedestrians and cyclists, while maintaining appropriate traffic capacity and discouraging high speeds.

Across the capital, many similar one way road systems are being successfully transformed into community friendly, safe and well planned two way streets.

On this website you can find out about the plans, our latest news and how to contact us. If you have any questions, please use the FAQs section, or contact us via this website, to get in touch.



Objectives of the scheme

  • Provide a significant improvement to the quality of public realm on Baker Street and throughout the target area
  • Reduce the dominance of traffic throughout the target area by removing the one-way system, introducing a two-way City Street environment on Baker Street; reduce vehicle speeds and thereby improve safety; reduce vehicle trip length (and therefore noise pollution and emissions) by improving accessibility;
  • Improve the environment for pedestrians by increasing available space, improving crossings and alleviating barriers to pedestrian movement such as Marylebone Road;
  • Improve public transport accessibility by providing bus access to Baker Street for northbound services, enhancing bus stops and connectivity between bus services, coaches and underground rail;
  • Improve conditions for cyclists and provide a key cycle link between the proposed CSH11 route at Regents Park to interface with the Westminster Cycle Grid at Upper Berkeley Street and George Street;
  • Ensure adequate kerbside capacity is maintained to provide affective loading, servicing and parking for local residents and businesses;
  • Avoid any unacceptable impacts to traffic operation, in particular on Marylebone Road, Oxford Street and Marble Arch;
  • Provide a safe environment for all road users.


Baker Street Two Way

Baker Street/Park Road
Artist's impression of the new road layout from early 2019


Baker Street Two Way

Baker Street/Marylebone Road
Artist's impression of the new road layout from early 2019


Baker Street Two Way

Baker Street/Blandford Street
Artist's impression of the new road layout from early 2019


Baker Street Two Way

Baker Street/Portman Square
Artist's impression of the new road layout from early 2019

About the project

TWO-WAY SWITCH

Improved streets for the local community.

Roads have re-opened as two-way

We can confirm that the following roads have re-opened as two-way:

  • Portman Street (between Oxford Street and Portman Square);
  • Gloucester Place;
  • Park Road (between Rossmore Road and Baker Street);
  • Baker Street; and
  • Orchard Street (between Wigmore Street and Oxford Street).

Also, the following roads have changed direction:

  • Ivor Place west of Gloucester Place - is now one-way westbound with contraflow cycling; and
  • Portman Mews South - is now one-way westbound.

Road Numbering

Gloucester Place will be numbered as the A4380, whilst Baker Street will continue to be numbered as the A41. Please note that both roads are retaining the ‘A-road’ classification and Gloucester Place has not been de-categorised. There are no two digit numbers available, so a four digit number has been assigned by the Department for Transport. It does not mean that Gloucester Place is less important than Baker Street.

Travel advice

Through traffic:

We would like to remind all users to take extra care. Drivers should be vigilant when driving on the new road layout and pedestrians need to remember to look both ways when crossing the roads.

To familiarise yourself with the new road layout, you can look at the following sources of information:



Baker Street Two Way

Pedestrians:

There are new signal controlled crossings at various points along the scheme.

Cyclists:

Summary of key new cycling infrastructure:

  • Gloucester Place - there are new cycle lanes both northbound and southbound, alongside advanced stop-lines at junctions. At the Marylebone Road junction there are dedicated traffic signals for cyclists mounted at a lower height.
  • Ivor Place - there is a new westbound contra-flow cycle lane between Park Road and Gloucester Place. At the junction with Park Road there is a dedicated traffic signal and cycle lane for eastbound cyclists.
  • Melcombe Street - between the junctions with Gloucester Place and Glentworth Street, there is a new eastbound contra-flow cycle lane. Please note that at the Glentworth Street junction, cyclists on the contra-flow cycle lane are only permitted to turn left onto Glentworth Street to head north.
  • Park Road - between the junctions with Ivor Place and Baker Street, there are new cycle lanes in both directions, as well as advanced stop lines.
  • Clarence Gate - there is a new northbound contra-flow cycle lane as you head towards Regent's Park, between the junction with Park Road and Outer Circle.
  • Western side of Dorset Square - just north of the Melcombe Street / Balcombe Street junction, there is a contra-flow cycle lane for cyclists heading north along Dorset Square and onto Balcombe Street.

Bus Passengers

Information regarding changes to bus routes is available via:


The diagram below shows where you can catch your bus.

Where to catch a bus

Coach Passengers

Coach routes have reverted to how they were beforehand.


Baker Street Northbound Traffic Restriction

For the northbound section of Baker Street between York Street and Marylebone Road, only Buses, Taxis and Cyclists are permitted. This restriction applies Monday to Friday 07:00 to 19:00. General traffic is advised to use Gloucester Place. Southbound traffic movements are unaffected by the restriction.



Proposed TRO Documentation

Traffic Order Cosultation related documentation - proposed


List of documents



    Drawings







Scheme Drawings

Scheme drawings A3

Back to Consultation Document »

Please select your area of interest by clicking on the below map to open the relevant drawings.

Section A Section B Section C Section D Section E Section F Section G Section H Section I Section J Section K Section L Section M Section N Section O Section P Section Q Section R Section S Section A Section B Section C Section D Section E Section F Section G Section H Section I Section J Section K Section L Section M Section N Section O Section P Section Q Section R Section S
Scheme Drawings

Scheme drawings A0

Back to Consultation Documents »

Please select your area of interest by clicking on the relevant drawings.


Baker Street Proposed Scheme North pdf 6.76 mb
Baker Street Proposed Scheme Centre pdf 4.67 mb
Baker Street Proposed Scheme South pdf 4.76 mb



 
 
 
 
 
 
 
 
 
 

the
team

<span>Limited cycling provision</span>

KEY PLAYERS

Scheme Drawings

Drawings of proposed changes, including benefits and disbenefits

Back to Consultation Documents »

Please select your area of interest by clicking on the below map to open the relevant drawings.

Ivor Place - A41 Gloucester Place Ivor Place A41 Park Road junction Clarence Gate Melcombe Place, Dorset Square and Melcombe Street A501 Marylebone Road  Balcombe Street  Upper Montagu Street A501 Marylebone Road  A41 Gloucester Place junction York Street  A41 Gloucester Place junction Ivor Place - A41 Gloucester Place Ivor Place A41 Park Road junction Clarence Gate Melcombe Place, Dorset Square and Melcombe Street A501 Marylebone Road  Balcombe Street  Upper Montagu Street A501 Marylebone Road  A41 Gloucester Place junction York Street  A41 Gloucester Place junction
Parking and Loading

Parking and Loading

Back to Project Documentation »

Please select your area of interest by clicking on the below map to open the relevant drawings.

Section 1 Section 3 Section 4 Section 5 Section 6 Section 7 Section 1 Section 2 Section 3 Section 4 Section 5 Section 6 Section 7
Before and after images

Before and after images

Back to Project Documentation »


BEFORE

Baker Street Marylebone Road junction looking north EXISTING

Baker Street Marylebone Road junction looking north – existing conditions.


AFTER

Baker Street Marylebone Road junction looking north PROPOSED


Baker Street Marylebone Road junction looking north – an artist's impression of current proposals showing two way traffic, additional footway area, footway repaving and redesigned crossings. All proposals will be subject to further detailed design development.





BEFORE

Dorset Square looking south EXISTING


Dorset Square looking south – existing conditions.


AFTER

Dorset Square looking south PROPOSED


Dorset Square looking south – an artist's impression of current proposals showing two way traffic, additional footway areas, footway repaving, redesigned junction and pedestrian crossings. All proposals will be subject to further detailed design development.





BEFORE

Gloucester Place looking north EXISTING


Gloucester Place looking north – existing conditions.


AFTER

Gloucester Place looking north PROPOSED


Gloucester Place looking north – an artist's impression of current proposals showing two way traffic, new cycle lanes, redesigned junction and pedestrian crossings. All proposals will be subject to further detailed design development.





BEFORE

Marylebone Road crossing EXISTING


Marylebone Road crossing – existing conditions.


AFTER

Marylebone Road crossing PROPOSED


Marylebone Road crossing – an artist's impression of current proposals showing a wider, direct pedestrian crossing. All proposals will be subject to further detailed design development.





BEFORE

Mid Baker Street looking north EXISTING


Mid Baker Street looking north – existing conditions.


AFTER

Mid Baker Street looking north PROPOSED


Mid Baker Street looking north – an artist's impression of current proposals showing two way traffic, wider footways and opportunities for more greenery. All proposals will be subject to further detailed design development.





BEFORE

Orchard Street seen from Portman Square EXISTING


Orchard Street seen from Portman Square – existing conditions.


AFTER

Orchard Street seen from Portman Square PROPOSED


Orchard Street seen from Portman Square – an artist's impression of current proposals showing two way traffic, redesigned junction and pedestrian crossings. All proposals will be subject to further detailed design development.





BEFORE

Portman Square looking northwest EXISTING


Portman Square looking northwest – existing conditions.


AFTER

Portman Square looking northwest PROPOSED


Portman Square looking north west – an artist's impression of current proposals showing two way traffic, footway repaving, redesigned junction and pedestrian crossings. All proposals will be subject to further detailed design development.


What does the project mean for me?

Residents

The proposals seek to return Marylebone to how it was originally intended; as a place for people.

Introducing two way traffic flow would reduce the need for traffic to follow unnecessarily long routes around the road system, which should reduce journey times. It will reduce the volume of traffic having to make circuitous routes on residential streets to access and leave locations across the area, and reduce the amount of turning movements at junctions.

The project proposes to make it easier and safer for residents to cross the road by introducing new controlled crossings and improving existing crossings.

As part of the wider improvements to the area, we propose to provide wider pavements along Baker Street and at Dorset Square, reduce street clutter and improve street lighting where it is most needed. The City Council is currently exploring opportunities to introduce more trees and green spaces.

Business

Removing the existing one way system would help create a safer, more pleasant neighbourhood where people want to spend time. By making it easier for residents and visitors to access local businesses, the project aims to help businesses grow.

The project would help prepare the area for the additional visitors and workers that can be expected when Crossrail completes in 2018 and in anticipation of the planned Chiltern Line upgrade into Marylebone station.

Businesses currently based on Baker Street and Gloucester Place would feel as if they are located in a historic and prestigious location rather than on an urban motorway.

Pedestrians

The project proposes significant improvements to pedestrian amenity in the area.

The project aims to provide up to 50 signal controlled crossings in the area, many of them new, relocated or upgraded. Pedestrians would also benefit from wider crossings with shorter crossing distances and new crossings in six locations which would enable pedestrians to cross safely in any direction.

Proposed wider, less cluttered pavements along Baker Street and at Dorset Square would help reduce pedestrian congestion and the risk of petty crime. This would be accompanied by improved street lighting and better signage.

The project also aims to create better pedestrian links to the major transport hubs at Bond Street, Baker Street and Marylebone stations.

Cyclists

The project aims to improve the facilities for cyclists by providing more places to park bicycles and new cycle lanes to connect the area with the London Cycle Grid. New advanced stoplines at junctions would help make cycling in the area both easier and safer.

Motorists

The current one way road system has sections where there is little delay followed by sections that can become heavily congested.

Motorists would be able to expect a smoother journey through the area, with an area wide traffic management strategy that removes the excessive traffic queues at existing traffic hotspots. By re-introducing two way traffic flow, motorists would have more flexibility in route choice with less need to follow unnecessarily long routes around the local residential road system.

Bus users

Creating two way traffic flow on Baker Street and Gloucester Place has long been an aspiration of Transport for London in order to improve access to buses and take passengers closer to their destinations.

The project aims to make the bus network easier to understand, by locating northbound and southbound services on the same street, where possible. Bus stops could also be combined and relocated to more suitable positions.

register for updates

Please register using the form to the right and remember to tick the ‘newsletter’ box if you would like to receive regular updates about the scheme via email.























Register for updates


Tick to receive our newsletter

THE TEAM

THE TEAM

Westminster City Council

Westminster City Council is the highway authority responsible for Baker Street and Gloucester Place south of Marylebone Road. These roads form part of the Strategic Route Network (SRN). The City Council is leading on the Baker Street Two Way project.

www.westminster.gov.uk

Transport for London

Transport for London (TfL) is the local government body responsible for most aspects of the transport system in Greater London, including major roads and bus services. Its role is to implement the Mayor of London’s transport strategy and to manage transport services across the capital. TfL is the highway authority responsible for Baker Street and Gloucester Place north of Marylebone Road and Marylebone Road itself. These roads form part of the Transport for London Road Network (TLRN).

www.tfl.gov.uk

Baker Street Quarter Partnership

Baker Street Quarter Partnership is a not-for-profit organisation that was established by a core group of businesses to bring newfound purpose and focus to the Baker Street and Marylebone area. Representing over 160 organisations it aims to create a thriving and prosperous area for the entire local community. Its three core areas of work focus on creating a high quality public realm, a vibrant area and providing member services. It is already making an impact on traffic reduction through its waste and freight consolidation programmes.

www.bakerstreetq.co.uk

The Portman Estate

The Portman Estate is located between Oxford Street and Edgware Road, and extends north towards the Marylebone Road and east to Manchester Square. The Estate is a mixture of residential, retail and office space and it aims to deliver a sense of community amongst its occupiers. Over recent years, The Portman Estate has restored many Georgian buildings to today’s high standards, and has created contemporary homes and offices that reflect their historical context.

It has also improved many areas, such as Portman Square and New Quebec Street, through co-investment with the Council.

www.portmanestate.co.uk

Latest News

Latest News

NEWS – Phase 4 works underway

All that remains is surface treatment to the carriageway along Baker Street, Gloucester Place, Orchard Street, Portman Square, and Portman Street. We are also completing the installation of the last of the directional signs and outstanding cycle racks.

See Building the Scheme for our night closures information.





NEWS – Phase 3 works complete and two-way switch now operational

The new road layout has taken effect. The roads have been operating as two-way roads since Sunday 24th February 2019.

This diagram shows the permitted movements.

Please note that along the northbound section of Baker Street, between York Street and Marylebone Road, only buses, taxis, cyclists and local access are permitted during the hours of 7am – 7pm Monday to Friday. Outside of these times all traffic is permitted to use this northbound section of Baker Street. No such restrictions are in place at weekends or public holidays.





NEWS – Phase 2 works are now complete and Phase 3 works are part way through.

This leaflet has more information about the planned works.





NEWS – Phase 2 works are nearing completion and Phase 3 works start 14th May 2018

This leaflet has more information about the planned works.





NEWS – Phase 1 works are now complete and Phase 2 works are underway

This leaflet has more information about the planned works.





NEWS – Works on Phase 1 are almost complete, and FM Conway will move off-site for the Christmas period (from 22nd December – 8th January).





NEWS – Phase 2 will start on 8th January 2018.

This leaflet has more information about the planned works.





NEWS – Councillors Visit Baker Street

https://twitter.com/CityWestminster/status/908263722430484481





NEWS - Works are moving forward

Works started on site on 24th July 2017. Phase 1 of these works will continue until December 2017.

A weekly update is sent out providing information about the on-going works and how it may affect you. please register here if you would like to receive these updates.

The images below show some of the construction taking place.

Baker Street Two Way

Excavation works at George Street with junction operating under temporary traffic lights



Baker Street Two Way

Construction mark ups at George Street junction



Baker Street Two Way

Image shows an example of the new paving



Baker Street Two Way

Works at Salisbury Place near Marylebone Road junction




NEWS - The transformation of Baker Street begins

View the Westminster City Council news article here: https://www.westminster.gov.uk/transformation-baker-street-begins-2





NEWS - Register for weekly email updates

If you would like to receive weekly emails about the works and how they may affect you, please register here





NEWS - Initial works notification letter

We will be in touch soon about how the works may affect you.

Baker Street Initial Works Notification Letter - Final

Find out more information about how your journey might be affected by visiting TFL's website – www.tfl.gov.uk/baker-street-roadworks





NEWS - Cabinet Member approval – May 2017

We have now received Cabinet Member approval to undertake implementation of the Baker Street Two Way scheme. A letter (Baker Street Initial Works Notification Letter - Final) has been sent out to all stakeholders.

Latest News

Issued Reports

Please find below links to reports presented to the Environment and Customer Services Policy and Scrutiny Committee on the 9th November 2015. This includes the Consultation report and responses to key issues.

Also below is a link to the Transport for London, Bus Consultation report.

FAQ's

Frequently Asked Questions

CHANGES TO ROAD LAYOUT

How will my journey be affected during construction?

http://www.bakerstreettwoway.co.uk/#switch

How long have the roads being operating as two-way roads?

The roads have been operating as two-way roads since Sunday 24th February 2019. A series of phased road closures were arranged from Thursday 21st February to enable the switch to take place safely.

Which roads were switched from one-way to two-way operation?

  • Portman Street (between Oxford Street and Portman Square);
  • Gloucester Place;
  • Park Road (between Rossmore Road and Baker Street);
  • Baker Street; and
  • Orchard Street (between Wigmore Street and Oxford Street).

The following roads have remained one-way but have changed direction:

  • Ivor Place west of Gloucester Place - now one-way westbound with contraflow cycling; and
  • Portman Mews South - now one-way westbound.

BAKER STREET NORTHBOUND TRAFFIC RESTRICTIONS

What are the traffic restrictions for northbound traffic on Baker Street?

Along the northbound section of Baker Street, between York Street and Marylebone Road, only buses, taxis, cyclists and local access are permitted during the hours of 7am – 7pm Monday to Friday. Outside of these times all traffic is permitted to use this northbound section of Baker Street. No such restrictions are in place at weekends or public holidays.

Why are there traffic restrictions for northbound traffic on Baker Street?

The restriction along the northbound section of Baker Street between York Street and Marylebone Road has been applied due to traffic capacity constraints at the Baker Street / Marylebone Road junction. We need to protect the signal ‘green time’ (when the traffic signal is showing green) given to the Marylebone Road eastbound and westbound traffic, which takes priority as it is part of the Priority Red Route, London Inner Ring Road.

We also need to make sure that southbound traffic from Baker Street (north) can turn right onto Marylebone Road effectively, and this means we need to restrict the volume of the opposing northbound traffic. We are therefore encouraging general northbound traffic (other than buses and taxis) to use Gloucester Place, which is also better connected as it allows left and right turns to join Marylebone Road, unlike Baker Street. Most of northbound TfL buses have now moved to Baker Street alongside most of the taxis. This has freed up capacity along Gloucester Place for northbound movements.

What is the advised route for northbound through traffic?

The A4380 Gloucester Place continues to provide a complete northbound route throughout the day between Oxford Street and the A501 Marylebone Road, and beyond to the A41 Park Road.

Baker Street now provides an alternative northbound route for more localised trips or through routes that cross the area, however it is advisable to avoid Baker Street where possible, because this is now the key bus corridor. The permitted movements diagram is available here

What are the prohibited movements for Baker Street northbound traffic at the Marylebone Road junction and why?

At the junction with Baker Street and Marylebone Road, there are only two permitted movements for northbound traffic:

1. Straight ahead (buses, cyclists and taxis only) – applies – Monday to Friday 7am – 7pm

Outside of these hours ALL traffic is permitted to travel northbound through the Baker Street/Marylebone Road junction

2. Left turn (buses and cyclists only at all times).

The left-turn restrictions are to allow buses to access the westbound bus lane on Marylebone Road and Stop Z on the Marylebone Road now that northbound buses have moved from Gloucester Place to Baker Street. Taxis are not permitted to turn left due to capacity issues at the junction. Instead they should use Gloucester Place. The exemption of taxis from the restriction on Baker Street Northbound is purely to allow them to provide services along Baker Street north of the Marylebone Road. No right-turn is provided at this junction for northbound traffic as it would affect capacity and conflict with Baker Street southbound movements. The permitted movements diagram is available here

BUSES

What has changed for the bus routes?

Southbound bus services are continuing to use Baker Street as before the switch. The majority of northbound bus services have moved from Gloucester Place to Baker Street. However, Route 2 towards Marylebone, Route 30 towards Hackney Wick, and Route 74 towards Baker Street Station, use Gloucester Place. Information regarding changes to bus routes is available via Transport for London

Who should I speak to about buses?

Transport for London are responsible for bus services, their routes and where they stop. To get in touch with them or to raise a complaint please email:customerservice@tfl.gov.uk.

COACHES

What has changed for the coach routes?

Coach services have not changed and are using the same routes as before. Northbound coach services are scheduled to use Gloucester Place. Southbound coaches that are scheduled to stop use Baker Street. Otherwise, southbound coach services can choose to use Baker Street or Gloucester Place. Please note that Westminster City Council have no authority to force coach operators to use a particular route.

Who should I speak to about coaches?

Transport for London are responsible for overseeing coach services across the capital. To get in touch with them or to raise a complaint please email: customerservice@tfl.gov.uk.

DORSET SQUARE COACH STOP

Why is there now a coach stop on the north-east corner of Dorset Square (on Gloucester Place)?

Since the introduction of a new signal controlled pedestrian crossing across Gloucester Place between Dorset Close and Marylebone Road, there is now insufficient space to accommodate all northbound coach services outside the Allsop Arms. Consequently, northbound coach services have been split between the stop outside the Allsop Arms and the stop on the north-east corner of Dorset Square.

The coach stop on the north-east corner of Dorset Square was previously a bus stop serving a large number of TfL day and night-time buses. There are fewer coaches using this stop than the number of buses previously using it, as these buses have now moved to Baker Street (freeing up capacity at this stop for coaches).

Why are northbound coaches not using Baker Street?

Capacity constraints at the Marylebone Road / Baker Street junction mean that it is not possible to move the northbound coaches to Baker Street as well. Most northbound TfL buses have now moved to Baker Street alongside most of the taxis. This has freed up capacity along Gloucester Place for northbound movements.

How do I report noise complaints about coach passengers or coach operators?

Transport for London are responsible for overseeing coach services across the capital. To get in touch with them or to raise a complaint please email: customerservice@tfl.gov.uk.

Why was a signal controlled pedestrian crossing provided on Gloucester Place between Dorset Close and Marylebone Road and not nearer to the junction with Marylebone Road?

If the pedestrian crossing over Gloucester Place was provided at the junction with Marylebone Road, this would require the introduction of a long pedestrian crossing stage at the junction and result in an unacceptable reduction in green time for priority traffic on the London Inner Ring Road. The pedestrian crossing location is restricted by the access requirement for the petrol filling station and also requires precise traffic signal timing to make sure traffic moves through the crossing at the right time and does not queue back across Marylebone Road, which would be a significant safety hazard. If the pedestrian crossing is located to the south of the access to the petrol filling station and is much closer to Marylebone Road, then there is a significant risk that either queues would form back across the junction, or vehicles turning onto Gloucester Place would not stop safely at the crossing.

GENERAL QUERIES

What was the total cost of the project?

Please refer to the Cabinet Member report publicly available via the Westminster City Council website for the project cost details: http://committees.westminster.gov.uk/mgIssueHistoryHome.aspx?IId=10724&Opt=0

When will all construction works associated with the delivery of the project be completed?

The major construction works associated with the scheme were completed by the end of June 2019 and there has been a significant reduced presence of our contractor FM Conway on-site since then. All works are scheduled to be completed by the end of August 2019.

What happened after the switch to two-way operation?

Following the switch to two-way operation on Sunday 24th February 2019, the scheme was subject to a 6-week moratorium period to allow traffic to get used to the new road layout. Our team also needed to finalise some areas that could only be completed with the roads operating as two-way. On Monday 1st April 2019, works resumed as part of Phase 4 of the scheme. Phase 4 works include:

  • Construction of permanent traffic islands;
  • Surface treatment works;
  • Installation of traffic signal loop detectors; and
  • Outstanding remedial works (carriageway resurfacing, tree planting and cycle rack installation).

With ‘permanent’ islands we refer to islands built with kerbs and slabs. Previous islands installed before the switch to two-way were temporary plastic islands bolted into the carriageway. The permanent islands could only be safely installed with the roads operating as two-way. Surface treatment works involve the application of:

  • A high friction anti-skid material (applied directly onto the asphalt surface) on the approaches to signal controlled junctions. High friction surfacing is a highly effective surface treatment proven to increase the skid resistance of asphalt roads. This material is installed over new asphalt in advance of most signal controlled junctions and is designed to aid vehicle braking.
  • Buff-coloured material at pedestrian crossings and the raised tables (Raised tables: carriageway surfaces at junctions that sit at a slightly higher level to provide a flush transition between the footway and the carriageway to make it easier for pedestrians to cross). This material at pedestrian crossing points and raised tables is designed to provide a visual warning to drivers and act as a traffic calming feature. Surface treatment application requires dry weather. As such the works have been scheduled to take place during the summer when weather conditions are typically more favourable for such work.

Information on night closures to enable these works to take place can be found at http://www.bakerstreettwoway.co.uk/#building and within the email updates.

What measures have been implemented to improve conditions for pedestrians?

The following enhancements for pedestrians have been made:

  • Additional signal controlled crossings including updated crossings across the Marylebone Road with shorter waiting times and the ability to cross Marylebone Road (outside Baker Street Underground station) in one go unlike the previous staggered arrangement;
  • Dedicated pedestrian stages at traffic signals to give pedestrians greater priority at junctions;
  • Wider footways;
  • New footway paving; and
  • Raised tables at junctions (carriageway surfaces that sit at a slightly higher level to provide a flush transition between the footway and the carriageway to make it easier for pedestrians to cross).

How do I keep up to date with the project?

The project website www.bakerstreettwoway.co.uk will be kept up to date periodically until Easter 2020. If you have subscribed to our newsletter, we will provide periodic updates - please visit http://www.bakerstreettwoway.co.uk/#contact to register.

GLOUCESTER PLACE / GEORGE STREET JUNCTION

What pedestrian crossing facilities are provided at this junction?

Four pedestrian crossings have been provided at this junction. There is a signal controlled pedestrian crossing on the southern side of the junction across Gloucester Place. Across the northern, eastern and western side of the junction, uncontrolled crossings have been provided. All pedestrian crossings have been provided with a flush surface (so there are no changes in level) and tactile paving to aid the visually impaired.

On the south-west corner of the junction we have installed a large buildout. This has reduced the crossing length on the western arm of the junction across George Street.

We would advise pedestrians to use the signal controlled pedestrian crossing on the southern side of the junction to cross Gloucester Place.

Why have signal controlled pedestrian crossings not been provided on every side of the junction?

The provision of formal pedestrian crossing facilities at the George Street junction is the same now as it was before the introduction of two-way traffic on Gloucester Place. During the design and traffic modelling stage, we did investigate whether or not additional controlled crossing facilities could be provided at this junction, but this would result in banning turning movements (which restricted accessibility to an unacceptable level) or introducing a pedestrian crossing stage. Traffic forecasts suggested that introducing a crossing stage would not be feasible because it would result in significant and unacceptable traffic congestion, with queues blocking back to Oxford Street. Nevertheless, now that the two way scheme is completed, there is an opportunity to review the operation of the junction and see if traffic flows are as high as predicted. We can then consider provision of further controlled crossing facilities. This review process is underway.

FAULTS, MAINTENANCE AND FEEDBACK

How do I report a maintenance or defect issue?

If you would like to raise a defect for the maintenance team to address please do so via: https://www.westminster.gov.uk/report-it. Items reported will be addressed as part of the Planned Preventative Maintenance Programme that Westminster City Council undertakes for its highway network.

How do I report an issue with a traffic signal?

To report a problem with a traffic signal please do so via: https://tfl.gov.uk/help-and-contact/contact-us-about-streets-and-other-road-issues

How do I report parking issues?

To report issues with parking, please do so via:

How do I report illegal driving or traffic contraventions?

To report illegal vehicles please do so via: https://www.westminster.gov.uk/traffic-contraventions-and-illegal-driving

Where can I obtain more information on parking?

To find out more information about parking in the City of Westminster please visit: https://www.westminster.gov.uk/parking

OTHER WORK IN THE AREA

What work is being undertaken on Oxford Street?

Footway paving is being renewed on Oxford Street as part of the Planned Preventative Maintenance Programme that Westminster City Council undertakes for its highway network. This work is not part of the two-way scheme.

What is happening to the footways around Portman Square?

Portman Square was paved in advance of the two-way scheme and some of the material has failed. The two-way scheme did not include in its scope the renewal of Portman Square footways as those activities are part of the Planned Preventative Maintenance Programme, however Westminster City Council is aware of the situation.

What is happening with regards to Cycle Superhighway 11?

Cycle Superhighway 11 (CS11) is not part of the two-way scheme and is being developed separately by Transport for London. A court ruling in September 2018 has prevented work from starting on CS11. Further information regarding CS11 can be found by visiting: https://tfl.gov.uk/travel-information/improvements-and-projects/cycle-superhighway-11

MONITORING STRATEGY

How many accidents have happened since the switch to two-way operation?

Since the switch to two-way, two incidents have been reported to Westminster City Council and the Metropolitan Police Service, neither of which were serious. The designs for the two-way scheme have undergone a rigorous road safety audit and were approved by an independent Road Safety Auditor.

What control measures have been in place since the switch to two-way monitoring?

The scheme has delivered additional and enhanced signal controlled pedestrian crossings at various points along the scheme including the junctions with Marylebone Road. In the run-up to and in the period after the switch to two-way operation, Westminster City Council have had several control measures in place. These have included the following:

  • Constantly monitoring the area as part of the Post-Implementation Review Strategy and coordinating with relevant parties when incidents are reported;
  • Pedestrian Crossing Marshals were on hand to help pedestrians cross the road for the first two weeks after the switch, and remind them to look both ways;
  • Comprehensive dialogue with a wide range of stakeholders to highlight the changes. This includes businesses, residents, public services, community facilities and neighbouring local authorities. It involved disseminating the changes through various communication channels including leafletting, face-to-face meetings, email updates, website posts and through social media;
  • At key locations “Look both ways” markings have been painted on the road and A-frame signs with the text “Look both ways” were deployed for three months after the switch;
  • Regular (usually weekly) email updates were sent to subscribers;
  • Coordination with TfL to optimise and modify traffic signal timings according to conditions;
  • Our partners have cascaded safety messages through their networks and channels; and
  • There have been public announcements on TfL services including local underground rail services informing passengers of the changes and the need to take care.

It should be noted that all road users have an individual responsibility to travel safely, be considerate of others and obey the highway code and all traffic laws.

How are you monitoring traffic following the switch to two-way operation?

The team is constantly monitoring the situation along the scheme extents. During October 2019, the final traffic surveys will be undertaken as part of the Monitoring Strategy. The results will be analysed and compared with traffic data that was collated before the implementation of the scheme. The purpose of this exercise is to ascertain how the switch to two-way operation has affected traffic patterns. A report will be published in December 2019 detailing the outcomes and any mitigation that may be required.

Why have traffic surveys been scheduled for October 2019?

We have undertaken localised traffic surveys in areas with safety or rat-run concerns from March, however we won’t be able to complete the surveys before October due to a number of factors:

  • 1. Road closures associated with Phase 4 of the scheme;
  • 2. Night-time road closures (20:00 to 06:00) for surface treatment works that are taking place on selective dates from the end of June until the middle of August;
  • 3. School summer holidays; and
  • 4. Road closures on Oxford Street and Marylebone High Street on selective dates for routine maintenance and the implementation of the Low Emission Neighbourhood scheme from now until the end of September.

Road closures distort traffic patterns and the routes used. Coupled with this, traffic is still getting used to the new road layout, and during the school summer holidays traffic volumes can be up to 1/3rd lower. Therefore, if any data was collated now or in the coming weeks, it would not be representative nor comparable to the data that was collected before the switch to two-way operation. Traffic data from before the switch to two-way operation was collated over an 18-hour period between 06:00 and 00:00 on neutral counting days.

Undertaking the surveys in October will have given sufficient time for drivers to have become accustomed to the new road layout and travel behaviours to have become normalised. By obtaining representative data, we will be able to better determine the type and extent of mitigation that may or may not be required.

TREES AND AIR QUALITY

How many trees were removed and why?

Altogether, 17 trees have been removed in Baker Street. Most of these trees were Italian Alders that were planted in the 1980s. At the time they were believed to be a good choice for a street tree. However, Westminster City Council has since discovered that their rapid rate of growth and propensity to grow towards the light and away from buildings results in the trees leaning over the carriageway creating a potential hazard to buses and other high-sided vehicles. This species also produces large surface roots which have a detrimental impact on the footway. Alders are also relatively short-lived trees. The majority of trees that have been removed had a predicted remaining safe life of between five and ten years.

How many new trees have been planted?

In total, 32 new trees have been planted. This means there has been a net gain of 15 new trees.

What species of tree have been planted and how were they planted?

The species chosen for Baker Street and George Street is London Plane (Plantanus x hispanica). Planes are the most common species of tree found in the capital. It was chosen due to its ability to adapt to urban environments. Pear trees were chosen for Gloucester Place to align to existing trees. Acer Campestre was chosen by Transport for London for new planting in Park Road.

All trees were planted directly in the ground with tree frames bounded by a resin material to maximise the available footway width to pedestrians. Box planting is not ideal in areas of high pedestrian footfall like Baker Street, as it reduces the available footway width.

What determined the location for new trees?

From the outset, the project team aimed at maximising the number of new trees in the area and planting new trees in the same locations as the old ones subject to ground investigation. Please note that the designers also had to account for high pedestrian footfalls and the need to maximise the available footway width at busy points. These included outside Baker Street Station, at bus stops, in and around crossing points and near to key commercial frontages.

During construction, tree planting was found to be unsuitable in certain locations. Numerous trial holes were excavated to determine the feasibility of specific sites. Unfortunately, Baker Street has a large amount of basement vaults underneath the existing footways that would restrict the growth of any new trees. In certain locations new trees could potentially impact on the structural integrity of the private structures. Furthermore, there are several utilities situated above basement roofs and in close but safe proximity to the footway surface. Consequently, these factors reduced the available depth and the quality of the soil. If new trees had been planted in these locations it would have hindered their health and longevity.

Who can I speak to regarding trees?

You can email the Streets and Parks team at Westminster City Council via: streetandparktrees@westminster.gov.uk

Baker Street north of the Marylebone Road is part of the Transport for London road network, it is owned and managed by TfL and not Westminster City Council or the Portman Estate. Any query for that specific area would be best directed to TfL.

What is being done to improve air quality in the area?

The Marylebone Low Emission Neighbourhood Scheme is introducing low level planting in Paddington Street and Marylebone High Street to help with air quality. For more information please visit the project website www.maryleboneLEN.org. or email info@maryleboneLEN.org.

The London Mayor has launched Breathe London. This new tool maps air quality around the capital, providing real-time updates and forecasts. Further information is available via: https://www.breathelondon.org/

Transport for London has launched its Let London Breathe Campaign. You may have noticed advertising in newspapers and on billboards. Further information about what this entails is available via: https://tfl.gov.uk/corporate/about-tfl/air-quality

On Monday 8th April 2019, the Ultra-Low Emission Zone (ULEZ) came into force within the same area of central London as the Congestion Charge. From 25 October 2021 the ULEZ boundary will be extended to create a single larger zone bounded by the North and South Circular Roads. Further information is available in the following links:

Accessibility

Accessibility

We are committed to ensuring everyone can access information on this website.

We are working towards making changes that mean this website is as easy and convenient to use as possible.

Web and accessibility standards

We make every effort to ensure that all pages on this site are valid to Hyper Text Mark-up Language (HTML5) and use valid Cascading Style Sheets (CSS3).

Queries

We are continuously seeking to improve the accessibility of the website. If you have any difficulties using this site that you believe we could address, please let us know at bakerstreet2w@wsp.com

It would be helpful if your e-mail contained the following:

  • What device you are accessing the site with, for example, a phone, a laptop or a tablet
  • Which browser you are using, for example, Chrome, Internet Explorer etc
  • A description of the issue
Privacy

Privacy

Effective date: May 1st, 2018

This page informs you of our policies regarding the collection, use, and disclosure of personal data when you use this website and the choices you have associated with that data.

We use your data to provide and improve this site. By using this website, you agree to the collection and use of information in accordance with this policy.

Information Collection And Use

We collect several different types of information for various purposes to provide and improve our Service to you.


Types of Data Collected

Personal Data

While using our website, we may ask you to provide us with certain personally identifiable information that can be used to contact or identify you ("Personal Data"). Personally identifiable information may include, but is not limited to:

  • Email address
  • First name and last name
  • Address, State, Province, ZIP/Postal code, City
  • Usage Data

Usage Data

We may also collect information how the website is accessed and used ("Usage Data"). This Usage Data may include information such as your computer's Internet Protocol address (e.g. IP address), browser type, browser version, the pages of our website that you visit, the time and date of your visit, the time spent on those pages, unique device identifiers and other diagnostic data.

Tracking & Cookies Data

We use do not use cookies on this website.

When someone visits http://bakerstreettwoway.co.uk we use a third party service, Google Analytics, to collect standard internet log information and details of visitor behaviour patterns. We do this to find out things such as the number of visitors to the various parts of the site. This information is only processed in a way which does not identify anyone. We do not make, and do not allow Google to make, any attempt to find out the identities of those visiting our website.


Use of Data

Baker Street Two Way Project uses the collected data for various purposes:

  • To provide and maintain the website
  • To notify you about changes to our website
  • To allow you to participate in interactive features of our Service when you choose to do so
  • To provide customer care and support
  • To provide analysis or valuable information so that we can improve the Service
  • To monitor the usage of the Service
  • To detect, prevent and address technical issues

Transfer Of Data

Your information, including Personal Data, may be transferred to — and maintained on — computers located outside of your state, province, country or other governmental jurisdiction where the data protection laws may differ than those from your jurisdiction.

If you are located outside United Kingdom and choose to provide information to us, please note that we transfer the data, including Personal Data, to United Kingdom and process it there.

Your consent to this Privacy Policy followed by your submission of such information represents your agreement to that transfer.

My Company LLC will take all steps reasonably necessary to ensure that your data is treated securely and in accordance with this Privacy Policy and no transfer of your Personal Data will take place to an organization or a country unless there are adequate controls in place including the security of your data and other personal information.


Disclosure Of Data

Legal Requirements

My Company LLC may disclose your Personal Data in the good faith belief that such action is necessary to:

  • To comply with a legal obligation
  • To protect and defend the rights or property of My Company LLC
  • To prevent or investigate possible wrongdoing in connection with the Service
  • To protect the personal safety of users of the Service or the public
  • To protect against legal liability

Security Of Data

The security of your data is important to us, but remember that no method of transmission over the Internet, or method of electronic storage is 100% secure. While we strive to use commercially acceptable means to protect your Personal Data, we cannot guarantee its absolute security.

Service Providers

We may employ third party companies and individuals to facilitate our website ("Service Providers"), to provide the website on our behalf, to perform website-related services or to assist us in analyzing how our website is used.

These third parties have access to your Personal Data only to perform these tasks on our behalf and are obligated not to disclose or use it for any other purpose.

Links To Other Sites

Our website may contain links to other sites that are not operated by us. If you click on a third party link, you will be directed to that third party's site. We strongly advise you to review the Privacy Policy of every site you visit.

We have no control over and assume no responsibility for the content, privacy policies or practices of any third party sites or services.

Children's Privacy

Our website does not address anyone under the age of 18 ("Children").

We do not knowingly collect personally identifiable information from anyone under the age of 18. If you are a parent or guardian and you are aware that your Children has provided us with Personal Data, please contact us. If we become aware that we have collected Personal Data from children without verification of parental consent, we take steps to remove that information from our servers.

Changes To This Privacy Policy

We may update our Privacy Policy from time to time. We will notify you of any changes by posting the new Privacy Policy on this page.

We will let you know via email and/or a prominent notice on our website, prior to the change becoming effective and update the "effective date" at the top of this Privacy Policy.

You are advised to review this Privacy Policy periodically for any changes. Changes to this Privacy Policy are effective when they are posted on this page.

Contact Us

If you have any questions about this Privacy Policy, please contact us:

  • By email: BSTW@westminster.gov.uk
Accessibility

Air Quality

What happens Next

KEY FEATURES AND ASSOCIATED BENEFITS

  • Introducing two way traffic flow would reduce the need for traffic to follow unnecessarily long routes around the road system, which should reduce journey times. It will reduce the volume of traffic having to make circuitous routes on residential streets to access and leave locations across the area, and reduce the amount of turning movements at junctions.
  • Improved facilities for cyclists by providing more places to park bicycles and new cycle lanes on Gloucester Place to connect the area with the London Cycle Grid. New advanced stop lines at junctions would help make cycling in the area both easier and safer.
  • Proposed wider, less cluttered pavements along Baker Street and at Dorset Square South and Melcombe Street would help reduce pedestrian congestion and the risk of petty crime. This would be accompanied by improved street lighting and better signage.
  • Provision of up to 50 signal controlled crossings in the area, many of them new, relocated or upgraded. Pedestrians would also benefit from wider crossings with shorter crossing distances and new crossings in six locations which would enable pedestrians to cross safely in any direction. In addition, it is proposed to improve pedestrian crossing facilities on Marylebone Road at its junction with Baker Street and Gloucester Place and Balcombe Street. This will help to improve pedestrian amenity and safety and reduce crossing time.
  • Bus network will be easier to understand, by locating northbound and southbound services on the same street, where possible. Bus stops could also be combined and relocated to more suitable positions.
  • Carriageway, footway and street lighting improvements will also be undertaken as part of this proposed scheme.

     

What happens Next

Consultation Documents


First round of consultation May - July 2015



Bus user consultation June-September 2015




Second round of consultation February – March 2016



Revised and updated project documents for second round of consultation




TMO Consultation November 2016 – January 2017






TMO map 01 2 3 4 5 6 7 8 9 10 11 12

01 2 3 4 5 6 7 8 9 10 11 12

Cabinet Member Reports

1. Cabinet Member Report – Baker Street Two Way - Feasibility Study


2. Cabinet Member Report – Baker Street Two Way - Initial design


3. Cabinet Member Report – Baker Street Two Way – Petition


4. Cabinet Member Report – Baker Street Two Way – Detailed design


5. Cabinet Member Report – Baker Street Two Way – Implementation